System Stability & Performance Testing
Performance testing wrapped up after intentionally creating system lag to gather meaningful data. The results are helping our technical teams identify optimization opportunities and define specific support requests for Microsoft. Good news: system stability is expected to normalize now that testing is complete, and the T5 environment will remain available for continued validation work.
Defect Resolution in Progress
Our technical teams are working through approximately 190 open items, including solution defects, security and access issues, process clarity gaps, and data quality concerns. The focus is on closing and finishing—not adding new scope. Each item is being classified as critical or nice-to-have to ensure we're prioritizing what matters most for a stable go-live.
Data Migration Milestone
Data Migration 7.5 is officially closed and reconciled, including GRNI and inventory! The team is now planning a corrected reload (7.6) of January data to address identified adjustments. Additional work continues on vendor bank data accuracy, final reconciliation rounds, and cutover planning aligned to our revised timeline.
Reporting & Analytics Moving Forward
Despite the timeline shift, our Inspire reporting teams continue making progress. AP aging, inventory, and cost analytics are being integrated and refined based on early user feedback. The goal? Deliver live analytical value before ERP go-live to improve adoption readiness and give our teams a head start on data-driven decision making.